3-1
Air Conditioning
Chapter 3. Air-Conditioning
This chapter explains air-conditioning requirements for the servers.
It includes the following topics:
Air-Conditioning System Features and Functions, on page 3-1
Air-Conditioning System Specifications, on page 3-2
Checks and Alarms, see page 3-5
CAUTION:
An air-conditioning system, compliant with the requirements of NF X44-101,
Class 4 000 000, dated June 1981 and with ISO 7730, is mandatory for the Bull NovaScale
Server.
Air-Conditioning System Features and Functions
Features
The Customer's air-conditioning specialist must select a fully automatic air-conditioning system
specially designed for the Data Processing Center. Radiators, fitted with thermostatic valves,
are acceptable in certain ancillary premises only.
The air-conditioning system must comprise at least two redundant assemblies, each providing
at least 66% of the total cooling power, to ensure continuity of operation.
Note:
The air-conditioning system will dry conditioned air. It is therefore mandatory for the
air-conditioning system to include a steam generation humidifier.
Functions
Temperature Control
Changes in temperature, in particular sudden changes in temperature, accelerate the ageing
of components. It is therefore important for ambient temperature to be stable and to be
maintained within the limits required for the system.
Hygrometry Control
A low level of hygrometry induces static electricity and a high level of hygrometry induces
corrosion and mildew. It is therefore important to comply with hygrometry specifications.
Heat Dissipation
When assessing heat dissipation / balance (in kW), the Customer's air-conditioning
specialist must take the following elements into account:
servers and extensions,
sunlight,
radiation from outside walls,
transmission of heat through walls separating the Computer Room from adjacent rooms,
lighting,
personnel,
air renewal.